NJ Turnpike Construction Interchange 14A Next Three Weeks

THREE WEEK SCHEDULE AS OF APRIL 21, 2017

The following work is scheduled over the next three weeks:
14A Interchange project next three weeks
Toll Plaza
East side (entering 14A): renovation of existing Toll Utility Building continues.
During the weekend of 04/21/17, from 9:00PM Friday through 1:00PM Saturday, asphalt paving construction work will be performed in Toll Lanes 3 & 4 after traffic passes through the Toll Plaza heading towards the Hudson County Extension. Traffic will be split before the Toll Plaza and motorists will need to choose to stay right for the eastbound extension (JC/NYC) or to the left for the westbound extension (Newark) before passing through the Toll Plaza. Once traffic passes through the Toll Plaza, motorists will not be able to switch lanes. A VMS sign will be placed at Toll Lanes 3 & 4 to direct traffic left and right. Work will be supported by Bayonne and State Police.
Continue reading NJ Turnpike Construction Interchange 14A Next Three Weeks