Bayonne Bridge Update

Mayor Jimmy Davis announced that the Port Authority of New York and New Jersey has advised the City of Bayonne concerning the latest developments in the Bayonne Bridge construction project.

The gantry continues to undergo load and performance testing. The gantry will begin to set segments of the bridge in January 2015.

Verizon and Cablevision continue installation of new cables inside street vaults. This work will require a curb closure and will involve a utility truck: Cable work continues on 1st Street. Work on Gertrude Street, 3rd Street, Juliette Street, and 4th Street has been completed. The cable activity is expected to be completed during mid-December 2014. Continue reading Bayonne Bridge Update