NJ Turnpike Interchange 14A Three Week Schedule Oct. 20, 2017

THREE WEEK SCHEDULE AS OF OCTOBER 20, 2017
 NJ Turnpike 14A Construction Project
NJ Turnpike Interchange 14A Three Week Schedule Oct. 20, 2017
The following work is scheduled over the next three weeks:
 
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Fall of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E between 51st Street and 53rd Street continues.
  • New bridge construction activities continue.
  • Asphalt paving will resume on Avenue E during the week of 10/23/17.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
  • On Sunday, 11/05/17, NJ Transit Light Rail Service between 34th Street Station in Bayonne and Danforth Avenue Station in Jersey City will be maintained via NJ Transit bus service, 3:00AM Sunday morning through 7:00PM Sunday evening. During this period, bridge construction work will be performed over the NJ Transit and Conrail train tracks.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Ramp structure construction to southbound Route 440 continues.
  • During the weekend of November 10, 2017, there will be weekend lane closures on northbound and southbound Route 440 between Pulaski Street and Harbor Drive for asphalt paving work. Work will be supported by Bayonne Police. 
Ramp Area East of Route 440
  • New ramp construction continues.
###
 
If you have any questions about the 14A Improvement Project, please call the toll-free hotline at 1-800-671-6872, or email [email protected] anytime. Thank you.
 
For full project details, contact information, traffic advisories, and informational pamphlets, please visit the NJTA 14A Website.
 
For information about the Bayonne Bridge, please click here

NJ Turnpike Interchange 14A Construction Schedule Next Three Weeks

THREE WEEK SCHEDULE AS OF JULY 14, 2017
 NJ Turnpike 14A Construction Project
The following work is scheduled over the next three weeks:
 
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • During the weekend of 07/14/17, 8:00PM Friday through 8:00AM Sunday, Toll Lanes 8 & 9 (exiting the Turnpike) will be closed for concrete paving work. This work will be supported by Bayonne Police.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the summer of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
  • During the evening of 07/14/17, 8:00PM to 7:00AM, roadway repair work will be performed on the ramp from westbound Hudson County Extension to Interchange 14A Toll Plaza. Minor traffic impacts are expected. This work will be supported by the New Jersey State Police. 
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • New bridge construction activities continue.  
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Ramp structure construction to southbound Route 440 continues.
Ramp Area East of Route 440
  • New ramp construction continues.
  • During the week of 07/17/17, nighttime detours of the southbound Route 440 Jughandle at Pulaski Street will be required for approximately one (1) week in support of bridge steel erection. Work will be supported by Bayonne Police.

###

 
If you have any questions about the 14A Improvement Project, please call the toll-free hotline at 1-800-671-6872, or email [email protected] anytime. Thank you.
 
For full project details, contact information, traffic advisories, and informational pamphlets, please visit the NJTA 14A Website.
 
For information about the Bayonne Bridge, please click here

Continue reading NJ Turnpike Interchange 14A Construction Schedule Next Three Weeks

NJ TURNPIKE INTERCHANGE 14A WORK SCHEDULE FOR NEXT THREE WEEKS

THREE WEEK SCHEDULE AS OF APRIL 14, 2017

 14A Interchange project

The following work is scheduled over the next three weeks:

 

Toll Plaza

  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • During the weekend of 04/21/17, concrete pavement construction will be performed in Toll Lane 8 upon exiting the Turnpike and asphalt pavement construction will be performed in Toll Lanes 3 & 4 upon entering the Turnpike. This work will be supported by Bayonne and the NJ State Police.

Ramps between the Toll Plaza and the Hudson County Extension (HCE)

  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.

Avenue E / Proposed Roundabout

  • New roadway construction on Avenue E near 53rd Street continues. 
  • Deep bridge foundation construction in dedicated work zones continues. This work will be supported by Bayonne Police as needed.
  • New bridge pier construction in dedicated work zones continues.

Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)

  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
  • During the weekend of 05/05/17 and 05/12/17, new bridge steel installation operations will be performed over NJ Transit’s Hudson-Bergen Light Rail and Conrail’s Industrial Track. During these periods, NJ Transit Light Rail service between 34th Street Station in Bayonne and Danforth Avenue Station in Jersey City will be maintained via NJ Transit bus service. 

Route 440 and Pulaski Street Intersection / Jughandle

  • Ramp roadway construction continues.
  • Median barrier construction on Route 440 continues.
  • Ramp structure construction to southbound Route 440 continues.
  • During the week of 04/24/17, northbound Route 440 traffic will be shifted left (two northbound lanes adjacent to median) and a work zone will be established on the right.

Ramp Area East of Route 440

  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • Roadway construction continues.

###

 

If you have any questions about the 14A Improvement Project, please call the toll-free hotline at 1-800-671-6872, or email [email protected] anytime. Thank you.

 

For full project details, contact information, traffic advisories, and informational pamphlets, please visit the NJTA 14A Website.

 

For information about the Bayonne Bridge, please click here

 

NJTurnpike 14A Interchange Improvement Project

NJTurnpike 14A Interchange Improvemnt ProjectThe NJ Turnpike 14A Interchange Improvement Project construction schedule for over  the next three weeks is as follows: 

 

Toll Plaza

  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • Reconstruction of Toll Lanes 11 & 12 continues.
  • During the weekend of 02/10/17, Toll Lanes 11-13 will open and Toll Lanes 8-10 will close. Please CLICK HERE for graphic.

Continue reading NJTurnpike 14A Interchange Improvement Project

NJ Turnpike 14A Weekend Construction Advisory January 28th, 2017

14A Traffic Advisory: Weekend of January 28, 2017
On Saturday, 01/28/17, 12:01AM to 4:00PM, the southbound Route 440 Jughandle at Pulaski Street will be closed for bridge demolition operations. Jughandle traffic will be detoured to the Prospect Avenue and 32nd Street Jughandle. Work will be supported by Bayonne Police. 
 
NOTE:  Previously forecasted disruptions during the weekend of

01/28/17 to NJ Transit’s Hudson-Bergen Light Rail services between 34th Street station in Bayonne and Danforth Avenue station in Jersey City will not be realized. Light Rail train service will not be impacted during this weekend.

Thank you for your patience. If you have additional questions, please call the toll free hotline at 1-800-671-6872. Please inform the operator that you have an urgent message and you’ll receive a return call within 24-hours.
### 
For full project details, contact information, and traffic advisories, please visit the NJTA 14A Website Â»
 
 

NJ TURNPIKE EXCHANGE 14A CONSTRUCTION NOTICE

14A constuction projectThe following work is scheduled over the next three weeks:
 
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building will continue.
  • Construction continues on the new east Toll Lane.
  • During the week of 02/29/16, a single toll exit lane will be closed, M-F, 8:00PM to 5:00AM.
  • Eastbound E 53rd Street is closed to through traffic at Avenue E (Toll Plaza) effective 11/09/15.  Drivers wishing to access the Toll Plaza must go down another eastbound street to Avenue E (51st, 49th, etc.) Access to local businesses (QuickChek, Value City, etc.) on E 53rd Street is maintained.  Westbound 53rd Street from the Toll Plaza to Broadway will not change.  The Eastbound closure is expected to be in place for six (6) months.  This is a major traffic change.
  • On or about March 6, 2016, eastbound 53rd Street, between Broadway and Avenue E, will be reopened. Normal two-way traffic will resume going in and out of Bayonne. Access to the Toll Plaza will be restored via the new roundabout south of 52nd Street. Motorists can follow the new roundabout to the Toll Plaza or continue south on Avenue E. For more information, please CLICK HERE to access the pamphlet.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Widening construction continues on the ramps to and from the west bound HCE.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges continues. This work will also be supported by Jersey City and Bayonne Police as needed.
  • Local street level work on Frontage Road continues.  This work will also be supported by Jersey City and Bayonne Police as needed.
  • Proposed Sign Structure Locations adjacent to the corner of Avenue B / E58th Street Corner, corner of Avenue C Structure and Garfield Avenue Structure (PSE&G Sub-Station), Toll Plaza Parking Area will be constructed. When needed, Bayonne PD or Jersey City PD will be asked to support this effort.
  • Work continues on a VMS Sign Structure under the Turnpike Bridge over Route 440, near the Newark Bay. Access is being provided from Route 440.
Avenue E / Proposed Roundabout
  • Deep foundation work on new bridge piers will continue. This work will be performed in dedicated work zones.
  • Bridge pier construction will continue in dedicated work zones.  Periodic closures of E52nd Street will be utilized.  This work will be supported by Bayonne Police.
  • Roadway drainage and pavement construction will continue.
  • Access to westbound 53rd Street from the Turnpike will be closed during the weekend of 02/26 through 02/28, 8:00PM Friday to 5:00PM Sunday for roadway reconstruction.  Access to local business including Value City Furniture and QuickChek will be maintained via 52nd Street. This work will be supported by Bayonne Police.
  • Southbound Avenue E will shift west to its permanent alignment, access to 52nd Street will be from southbound Avenue E only and 51st Street will be changed to a right turn only onto southbound Avenue E during the weekend of March 6, 2016.
  • Southbound Avenue E traffic will be diverted to 52nd Street on Monday, 02/29, 8:00AM to 3:30PM, for roadway reconstruction.  This work will be supported by Bayonne Police.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • A two-way traffic pattern has been implemented on the bridge ramp from Port Jersey Boulevard to the Toll Plaza.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
Route 440 and Pulaski Street Intersection / Jughandle
  • The southbound Route 440 Jughandle at Pulaski Street has been reduced to a single lane. Deep sewer construction continues.
  • Temporary traffic signal work is being performed in the intersection.  Temporary signals are scheduled to be activated the week of 02/29/16.
  • Utility relocation work will continue on Pulaski Street at Route 440. This work will be supported by Bayonne and Jersey City Police.
Ramp Area East of Route 440
  • Ground improvement and new ramp construction continues.
  • Retaining wall construction continues.
  • Deep sewer relocation work will continue.
  • Bridge abutment construction will begin.
###
If you have any questions about the 14A Improvement Project, please call the toll-free hotline at 1-800-671-6872, or e-mail [email protected] anytime. Thank you.
For full project details, contact information, and traffic advisories, and informational pamphlets, please visit the NJTA 14A Website.
For information about the Bayonne Bridge, please click here.

Continue reading NJ TURNPIKE EXCHANGE 14A CONSTRUCTION NOTICE