NJ TURNPIKE INTERCHANGE 14A WORK SCHEDULE FOR NEXT THREE WEEKS

THREE WEEK SCHEDULE AS OF APRIL 14, 2017

 14A Interchange project

The following work is scheduled over the next three weeks:

 

Toll Plaza

  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • During the weekend of 04/21/17, concrete pavement construction will be performed in Toll Lane 8 upon exiting the Turnpike and asphalt pavement construction will be performed in Toll Lanes 3 & 4 upon entering the Turnpike. This work will be supported by Bayonne and the NJ State Police.

Ramps between the Toll Plaza and the Hudson County Extension (HCE)

  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.

Avenue E / Proposed Roundabout

  • New roadway construction on Avenue E near 53rd Street continues. 
  • Deep bridge foundation construction in dedicated work zones continues. This work will be supported by Bayonne Police as needed.
  • New bridge pier construction in dedicated work zones continues.

Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)

  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
  • During the weekend of 05/05/17 and 05/12/17, new bridge steel installation operations will be performed over NJ Transit’s Hudson-Bergen Light Rail and Conrail’s Industrial Track. During these periods, NJ Transit Light Rail service between 34th Street Station in Bayonne and Danforth Avenue Station in Jersey City will be maintained via NJ Transit bus service. 

Route 440 and Pulaski Street Intersection / Jughandle

  • Ramp roadway construction continues.
  • Median barrier construction on Route 440 continues.
  • Ramp structure construction to southbound Route 440 continues.
  • During the week of 04/24/17, northbound Route 440 traffic will be shifted left (two northbound lanes adjacent to median) and a work zone will be established on the right.

Ramp Area East of Route 440

  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • Roadway construction continues.

###

 

If you have any questions about the 14A Improvement Project, please call the toll-free hotline at 1-800-671-6872, or email [email protected] anytime. Thank you.

 

For full project details, contact information, traffic advisories, and informational pamphlets, please visit the NJTA 14A Website.

 

For information about the Bayonne Bridge, please click here

 

New Jersey Turnpike 14A Interchange Construction Updates

New Jersey Turnpike 14A Interchange Construction updates.The following work is scheduled over the next three weeks:

14A constuction project

Toll Plaza

  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • Reconstruction of Toll Lanes 8-10 continues.
  • A new traffic pattern was implemented at the Toll Plaza on 2/10/17. Please CLICK HERE for graphic.

Ramps between the Toll Plaza and the Hudson County Extension (HCE)

  • Widening construction on the ramps to and from the westbound and eastbound HCE is complete to the extent possible and the final alignment has been implemented. Asphalt resurfacing of the ramps will be performed in 2017.
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the Spring of 2017. This work will be supported by Jersey City and Bayonne Police as needed.

Avenue E / Proposed Roundabout

  • Continue new roadway construction on Avenue E near 53rd Street. 
  • Continue deep bridge foundation construction in dedicated work zones. This work will be supported by Bayonne Police as needed.
  • On 03/08/17, a daytime detour of northbound Avenue E will be used, 10:00AM to 2:00PM. During this period, northbound Avenue E traffic, between 50th Street and 51st Street, will be diverted to Broadway to accommodate bridge structural steel erection. The expected duration of the detour is four (4) hours.  This work will be supported by Bayonne Police.

Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)

  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.

Route 440 and Pulaski Street Intersection / Jughandle

  • Ramp roadway construction continues.
  • Continue new bridge pier construction for the new structure to southbound Route 440.

Ramp Area East of Route 440

  • New ramp construction continues.
  • Retaining wall construction continues.
  • Bridge deck construction on the bridge structure over Pulaski Street continues.
  • During the evenings of 03/09 and 03/10/17, nighttime detours of northbound Route 440 will be required immediately north of Pulaski Street, 8:00PM to 4:00AM, for bridge structural steel erection. Work will be supported by Bayonne and Jersey City PD.

###

 

If you have any questions about the 14A Improvement Project, please call the toll-free hotline at 1-800-671-6872, or email [email protected] anytime. Thank you.

 

For full project details, contact information, traffic advisories, and informational pamphlets, please visit the NJTA 14A Website.

 