Tag Archives: construction delays on NJ Turnpike

New Jersey Turnpike 14A Interchange Construction Schedule

New Jersey Turnpike 14A interchange Construction Schedule

The following work is scheduled over the next three weeks:

Toll Plaza
East side (entering the Turnpike) renovation of existing Toll Utility Building continues.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
No work planned.
Avenue E / Proposed Roundabout
During the week of 05/07/18 through 05/21/18, daytime lane closures will be utilized for clean up work between 53rd Street and 50th Street. This work will be supported by Bayonne Police as needed.
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited.
Route 440 and Pulaski Street Intersection / Jughandle
Continue traffic signal construction on Route 440.
During the week of 05/07/18 through 05/21/18, nighttime nighttime lane closures will be utilized for clean up work within the Jughandle and on 440. This work will be supported by Bayonne Police as needed.
Ramp Area East of Route 440
Continue traffic signal construction on Port Jersey Boulevard.
During the week of 05/07/18 through 05/21/18, clean up work will continue. This work will be supported by Bayonne Police as needed.
###

If you have any questions about the 14A Improvement Project, please call the toll-free hotline at 1-800-671-6872, or email [email protected] anytime. Thank you.

For full project details, contact information, traffic advisories, and informational pamphlets, please visit the NJTA 14A Website.

 

NJTurnpike 14A Interchange Improvement Project

NJTurnpike 14A Interchange Improvemnt ProjectThe NJ Turnpike 14A Interchange Improvement Project construction schedule for over  the next three weeks is as follows: 

 

Toll Plaza

  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • Reconstruction of Toll Lanes 11 & 12 continues.
  • During the weekend of 02/10/17, Toll Lanes 11-13 will open and Toll Lanes 8-10 will close. Please CLICK HERE for graphic.

Continue reading NJTurnpike 14A Interchange Improvement Project