NJ Turnpike Interchange 14A Construction Schedule Next Three Weeks

THREE WEEK SCHEDULE AS OF JULY 14, 2017
 NJ Turnpike 14A Construction Project
The following work is scheduled over the next three weeks:
 
Toll Plaza
  • East side (entering 14A): renovation of existing Toll Utility Building continues.
  • During the weekend of 07/14/17, 8:00PM Friday through 8:00AM Sunday, Toll Lanes 8 & 9 (exiting the Turnpike) will be closed for concrete paving work. This work will be supported by Bayonne Police.
Ramps between the Toll Plaza and the Hudson County Extension (HCE)
  • Local street level work at Garfield, Avenue C and JFK Boulevard bridges will resume in the summer of 2017. This work will be supported by Jersey City and Bayonne Police as needed.
  • During the evening of 07/14/17, 8:00PM to 7:00AM, roadway repair work will be performed on the ramp from westbound Hudson County Extension to Interchange 14A Toll Plaza. Minor traffic impacts are expected. This work will be supported by the New Jersey State Police. 
Avenue E / Proposed Roundabout
  • New roadway construction on Avenue E near 53rd Street continues.
  • New bridge construction activities continue.  
Connector Bridge (Bridge from the Toll Plaza to Port Jersey Boulevard)
  • Traffic was shifted onto the new Connector Bridge in a two-way temporary traffic pattern. Please CLICK HERE for graphic.
  • Pedestrian usage of the bridge for access to and from Port Jersey Boulevard continues to be prohibited. Please CLICK HERE for shuttle bus pamphlet.
Route 440 and Pulaski Street Intersection / Jughandle
  • Ramp roadway construction continues.
  • Ramp structure construction to southbound Route 440 continues.
Ramp Area East of Route 440
  • New ramp construction continues.
  • During the week of 07/17/17, nighttime detours of the southbound Route 440 Jughandle at Pulaski Street will be required for approximately one (1) week in support of bridge steel erection. Work will be supported by Bayonne Police.

###

 
If you have any questions about the 14A Improvement Project, please call the toll-free hotline at 1-800-671-6872, or email [email protected] anytime. Thank you.
 
For full project details, contact information, traffic advisories, and informational pamphlets, please visit the NJTA 14A Website.
 
For information about the Bayonne Bridge, please click here